May 31, 2017
|
EPA Announces 2017 Brownfields Program Awards
|
Oct. 1, 2017
|
Grant period begins
|
Oct. 25, 2017
|
Assessment consultant Request for Qualification advertisement begins
|
February 20, 2018
|
City Council approved a Contract for Professional Services with TRC for the Community-wide Environmental Assessment Project
|
June 15, 2018
|
EPA approved Phase I assessment of Site 1, Riverview Park.
|
August 6, 2018
|
EPA approval Phase I and II assessment of Site 2, "the Berm" (27 Marina Blvd.)
|
August 23, 2018
|
EPA approval of Sampling Plan and Phase II assessment of Site 1, Riverview Park
|
Oct. 29, 2018
|
EPA approval of Sampling Plan and Phase II assessment of Site 2, "the Berm"
|
Dec. 31, 2018
|
Phase II assessment of Site 1, Riverview Park Complete
|
February 21, 2019 |
Phase II assessment of Site 2, The Berm Complete
|
February 26, 2019 |
EPA approval of Phase I and II assessment of Site 3 (corner of California x Harbor)
|
February 26, 2019 |
EPA approval of Phase I and II assessment of Site 4 (corner of Bliss x Harbor) |
March 3, 2019 |
EPA approval of Phase I and II assessment of Site 5 (895 E. 3rd Street) |
June 5, 2019 |
US EPA awards the City of Pittsburg $800,000 Multipurpose Grant for assessment, cleanup, and reuse planning. |
June 6, 2019 |
Completion of Phase I assessments of Sites 3 and 4. Recommendations for Phase II assessments approved by EPA. |
July 16, 2019 |
Sampling and Analysis Plans sent to EPA for review for Phase II work on Sites 3& 4. |
July 30, 2019 |
EPA approval of Phase I and II assessment of five sites (site 6: APN 073-042-023, site 7: 12 Industry Rd, site 8: 8 Industry Rd, site 9: former Railroad Right of Way on Industry Rd, and site 10: City owned Right of Way on Harbor St.) |
August 21, 2019 |
Sampling and Analysis Plans approved for sites 3 & 4 |
December 18, 2019 |
Sampling and Analysis Plan submitted for sites 7 and 8 |
January 13, 2020 |
Revitalization Planning consultant Request for Qualification advertisement begins |
January 30, 2020 |
Sampling and Analysis Plan approved for sites 7 and 8 |
February 13, 2020 |
Phase I assessment complete for site 6 |
February 25, 2020 |
EPA approval of Phase I and Phase II assessment of site 11: 2575 Railroad Avenue. No further action. Water Board oversight in place. |
February 28, 2020 |
EPA approval of Phase I and Phase II assessment of site 12: 2101 Railroad Avenue |
April 6, 2020 |
City Council approval of Professional Services contract with De Novo Planning Group for Site Reuse Assessment and Revitalization Plan Services per the 2019 Multipurpose Brownfields Grant |
April 7, 2020 |
Phase I assessment complete for site 12. |
June 11, 2020 |
Site 15 EPA approval of eligibility received. Commence Revitalization Planning. |
June 18, 2020 |
SAP approved for site 12 |
July 1, 2020 |
EPA approval of Phase I and Phase II assessment of site 13: 385-495 E. 3rd Street |
July 21, 2020 |
Phase II assessment commences at site 12 |
August 20, 2020 |
Virtual Community Workshop & Survey for Revitalization Plan opens |
August 24, 2929 |
Site 13 Phase I assessment complete |
September 27, 2020 |
Virtual Community Workshop & Survey for Revitalization Plan closes |
October 6, 2020 |
Sites 7 and 8 SAP shared with DTSC |
December 7, 2020 |
EPA returns site 13 SAP with comments required for approval |
December 7, 2020 |
Phase II assessment complete at site 12 |
January 19, 2021 |
Phase II assessments start for sites 3 and 4 |
March 15, 2021 |
Phase II assessments complete for sites 3 and 4 |
March 26, 2021 |
Phase II assessment of site 13 begins |
July 19, 2021 |
City Council approval of a contract for Remediation Design and Planning Services with TRC |
Aug. 16, 2021 |
City Council approval of Amendment 1 to contract for Community-wide Environmental Assessment Services with TRC |
Aug. 31, 2021 |
Updated site 13 SAP submitted to EPA for review |
January 12, 2022 |
Site 13 SAP approved by EPA |
April 4, 2022 |
Phase II complete for Site 13
City applies for Department of Toxic Substances Control Equitable Communities Revitalization Grant to design and conduct remediation of Site 13
|
June 17, 2022 |
City receives notice of potential DTSC ECRG funding for design and cleanup of Site 13. Status pending. |
July 14, 2022 |
City submits eligibility form for site assessments of a new site, Site 14, the Granted Tidelands Wharf. |
August, 2022 |
City receives approval for Phase I assessment of Granted Tidelands Wharf under Assessment Grant and approval for development of Reuse Plans under Multipurpose Grant. |
August 16, 2022 |
City executes a consultant agreement with Anchor QEA for a Feasibility Study of the Granted Tidelands Wharf, Site 14 |
September 1, 2022 |
City executes a consultant agreement with Anchor QEA for Phase I of the Granted Tidelands Wharf, Site 14 |
November 30, 2022 |
City fully expends and closes out US EPA Assessment Grant |
December 20, 2022 |
Phase I of the Granted Tidelands Wharf, Site 14 completed |
February 16, 2023 |
Draft Tidelands Wharf, Site 14 feasibility study received. |
June 23, 2023 |
City enters into $534,437 Grant Agreement with DTSC for cleanup of Site 13 |
June 26, 2023 |
Site 15 Revitalization Plan draft received. |
September 2023 |
City enters into Cost Recovery Agreement with SF Bay Regional Water Board (Water Board) for Site 13 cleanup |
September 19, 2023 |
City received draft Corrective Action Plan for City-owned East 3rd Street parcels (site 13) -Funded by ECRG |
September 27, 2023 |
Draft Corrective Action Plan for Site 13 sent to Water Board for review - funded by ECRG |
October 4, 2023 |
Site Eligibility Form submitted to EPA for 8th Street Linear Park, Site 16 |
November 7, 2023 |
Site Eligibility Form approved by EPA for 8th Street Linear Park, Site 16 |
November 8, 2023 |
Site 13 Corrective Action Plan approved by Water Board. |
December 13, 2023 |
Eligibility for Johns Manville North (Site 17), Johns Manville South (Site 18), H Cycle (Site 19) Sites approved |
March 8, 2024 |
Groundwater Monitoring Plan for Site 13 cleanup submitted to Water Board for review |
April 24, 2024 |
Groundwater Monitoring Plan for Site 13 cleanup approved by Water Board. |
June 7, 2025 |
Site 13 out to bid for construction contract |